Civil and assembly works for the construction of substations 110 / 20 kV in Berat, Porto Romano and Elbasan, Albania The civil works for the construction of substations includes: Access to the site, land/soil preparation, retaining wall, grounding network system, outside fencing, roads, drainage network system, foundations and bedplates, fire wall, cable channeling, control building. The total area of each substation is 1,800 m2.
Power Supply for “Mother Teresa” International Airport, Rinas Albania1.Building a new 20kV high voltage substation with 20kV ring and the cable supplied for    the connection to: - new terminal- existing terminal include the tower- Existing AFL substation- New Cargo and other Buildings- New Tower2.  New substation 0.4kV Low Voltage Power     Supply for the tower substation,     AIR centre and the AFL substation.3.  New Extra Low Voltage infrastructure for ITnetwork,     telecommunication, CCTV etc, extra low voltage cabling.4.  New Emergency Power Supply for the Terminal and Cargo building.      Emergency power supply new substation for the existing tower building.5.  Fence lighting. 
Construction of new substationin Tirana. Sub-Contracted by “A.B.B.”company – Italy.Value of construction: 154 000 EURO
Name of Project: Construction of 400 kV Transmission line Hani Hotit - Vau DejesLength 80 kmThe construction of this transmission line includes:• Construction of access roads (75 km new access road and 40 km reconstruction of existing)• Construction of 202 foundations for towers• Earthing 
Name of Project: Construction of 110 kv overhead line Berat – Kucova – Uznova, AlbaniaLength 13.3 kmThe construction of this line includes:• Construction of foundations for towers• Grounding• Erection works• Stringing
1